Material Plant BOM Usage Alternative BOM Change Number Valid From Valid to Revision Level Required Quantity
CS03 CS09 CS15 CS14 CS12 CS11
Responsible for giving information related to Bill of Materials. Comparison of BOM between two Materials.
Production
2
Work Center Information System
Work center Plant Work center cat. Person responsible Capacity category Capacity planner Name of hierarch Plant Controlling area Cost center
CR60 CR05
In this report Machines used for manufacturing are displayed. Labor work center is also displayed.
Production
3
Operation Analysis Dates Selection
Plant Work center Material Order Operation/Activity Date Exception
MCPB MCPY MCPK MCPQ
This report is used to extract the information of operation quantity, scrap quantity, lead time, target lead time.
Production
4
Material Analysis
Plant MRP controller Material Month Exception
MCPW MCPF MCPO MC89
Used to give information of target against actual lead time. Planned ordered quantity against actual ordered quantity. Planned cost against actual cost.
Production
5
Operation Analysis: Selection
Plant Work center Material Order Operation/Activity
MCP1 MCP3 MCP5 MCPB MCPU MCPW
The order information system is a tool for shop floor control with a reporting function for production orders and planned orders. These reports are useful in discreet manufacturing set up.
Always use Pretty Printer and Extended Program Check before releasing the code.
Do not leave unused code in the program. Comment the code thoroughly. Align the comments and the Code. Follow the SAP Standards and SAP Best Practices guidelines. It’s a good practice to take a dump of the code on your local drive.
No comments:
Post a Comment